| Removal |
| 1. | Turn the ignition switch OFF and disconnect the battery (-) terminal. |
| 2. | Remove the engine room under cover. (Refer to Engine Mechanical System - "Engine Room Under Cover") |
| 3. | Drain the hydraulic oil from the reservoir using a syringe.
|
| 4. | DIsconnect the reservoir hose (A).
|
| 5. | Remove the reservoir (A) after loosening the bolts.
|
| Installation |
| 1. | Install in the reverse order of removal. |
| 2. | Refill the specified lubricants in the reservoir and then perform the air bleeding using the GDS.
|
Components 1. Clutch disc2. Clutch cover3. Concentric slave cylinder4. Hybrid motor assembly5. Engine clutch actuator6. Reservoir
General Information1.Check & Change intervals Check Change Capacity Specified lubricants 15000 km / 1 years(9000 miles / 1years) 40000 km(25000 miles)Remove air from the hydraulic line and theninject hydraulic fluid to the reservoir so that it comes between the MAX and MIN levels of the reservoir.
InspectionOperating Logic Test (Manual only)Inspect the PTC operation by confirmation logic as follows.1.Entering(1)Set the Floor mode and maximum heating position.(2)Turn off the blower switch.(3)Press the intake (recirculation) button 5 times or more.
Replacement1.Remove the battery (-) terminal.2.Remove the engine room under cover.(Refer to Engine Mechanical System - "Engine Room Under Cover")3.Remove the heater hose (A) and AEWP hose (B).4.Disconnect the lock pin to remove the heater hose pump connector (A).