Removal • Be sure to read and follow the "General Safety Information and Caution" before doing any work related with the high voltage system.
DescriptionBattery fuse box is located on the side of the high voltage battery pack. It prevents cells from being damaged by external factors, such as short or overcurrent.
InspectionOperating Logic Test (Manual only)Inspect the PTC operation by confirmation logic as follows.1.Entering(1)Set the Floor mode and maximum heating position.(2)Turn off the blower switch.(3)Press the intake (recirculation) button 5 times or more.
Inspection1.Turn the ignition switch OFF. 2.Disconnect the auto defogging connector. 3.Verify that the auto defogging actuator operates to the open position when connecting 12V to terminal 3 and grounding terminal 4. Verify that the auto defogging actuator operates to the close position when connected in reverse.